Nothing really happened over the holidays but we did get an updated schedule from our FM:

  • Replacement cabinets should be in this week or next
  • Once those are installed we can get ready for flooring
  • Gas line should be installed by 12/30 per Columbia Gas
  • Storm laterals to be installed over the next week (had to find a new excavator as ours stopped responding to calls/e-mails)
  • Next week we put in the gas meter and start up the furnace (heat is essential)
  • Painter should be by 1/6-1/8 to finish paint and staining
  • Week of the 11th for final electric, final plumbing, and preparation for flooring