- Replacement cabinets should be in this week or next
- Once those are installed we can get ready for flooring
- Gas line should be installed by 12/30 per Columbia Gas
- Storm laterals to be installed over the next week (had to find a new excavator as ours stopped responding to calls/e-mails)
- Next week we put in the gas meter and start up the furnace (heat is essential)
- Painter should be by 1/6-1/8 to finish paint and staining
- Week of the 11th for final electric, final plumbing, and preparation for flooring
Our journey of building a new home with Wayne Homes. This is our daily account of building our custom Hampton home. We hope you find this informative and helpful, as we are realistic and honest 1st generation builders. If our photos, entries, and opinions help you make the decision to build your home with Wayne Homes, please mention our blog. We would greatly appreciate the referral!
Sunday, December 27, 2015
Day 134 - New Schedule
Nothing really happened over the holidays but we did get an updated schedule from our FM: