Talked with our FM and he provided me with the following schedule:
- 9/21 - Finish framing
- 9/22 - Shingles being delivered
- 9/23 - Roofers coming to do the roof; garage door installation; AC/furnace roughing
- 9/24 - AC/furnace roughing
- 9/25 - Fireplace install
- 9/28 - Plumbing
- 9/29 - Electrical walk through with electrician (need to ask him about running speaker wire)
- 9/30 - Finish electrical
- 10/1-10/2 - Inspections
- Next steps: Concrete poured and cut; trades back to do the downstairs bathroom
Documenting some questions we had:
- When does the siding go on? - after the concrete is poured and cut
- We noticed the external doors delivered were off-white, do those get painted? - Yes
- Are the stairs part of the framing scheduled to complete by 9/21? - Yes
- Are there locks put on doors immediately after installation? - No, those go on later
- Can we set aside a date for me to run speaker wire along with Coax and Cat5? - Yes
Stairs going up but not down yet. |
Stairs are working. |
View from the loft. |
He likes his new bedroom. |
Jefferson building in his bedroom closet. |
She loves her new walk-in closet. |
Master bedroom is huge. |
Master bathroom. |