Tuesday, January 19, 2016

Day 157 - Flooring Started & Downspout Trenching

Today was a busy day at the house with flooring being delivered, prepping flooring, and our new excavator (Arron) digging up the yard and putting in the laterals for the downspouts.  This should help some of the drainage issues around the property.  Both flooring and trenching should continue into tomorrow.

We also made another big decision.  The AC unit was installed on the East side of the house to our displeasure.  After talking with our FM (and even though he suggested otherwise), we've decided to move it to the back northwest corner on the ground on a stand until we can have a permanent concrete slab poured.  We just didn't want to see that on the side of the house where we intend to put a sidewalk to the backyard.

You can see here that the AC unit just sticks out like a sore thumb.